Reporting meeting of Deputy General Director for operation with employees of structural subdivision of Beineu-Shymkent Gas Pipeline LLP

On November 10, 2016 First Deputy General Director  for operation T. Adilov held a meeting with employees of structural subdivisions of Beineu-Shymkent Gas Pipeline LLP (hereinafter – BSGP LLP).

1

In the course of the meeting there have been summarized results of production and technical (hereinafter PTD), production and dispatch (hereinafter PTD) departments over 10 years of current year, other tasks for November, December, 2016 have been also discussed. One priority task, according to T.Adilov is commissioning of three gas turbine units (hereinafter GTU) at Bozoy compressor station (hereinafter Bozoy CS).

T.Adilov particularly emphasized the importance of Bozoy CS start-up by December 14, 2016 and highlighted completion of all preparatory works to the specified date.

2

In the course of implementation of the assigned tasks there have been also discussed problematic issues which require immediate resolution, including organization of training of operating personnel of Operator and personnel of BSGP LLP in terms of operation of installed equipment at Bozoy CS. Further on, with a view of organization of planning of operating regime of BBS MGP and GTU at Bozoy CS there has been made a decision to develop a scenario for filling of GTU. In general the plan and report from PTD and PDD departments have been approved.

At the end of the reporting meeting Deputy General Director for operation T. Adilov thanked all for efficient work and wished all employees success in implementation of the set goals.

antalya escort escort antalya sex hikaye erotik hikaye porno hikaye ensest hikaye